Update on road works - Sandy Lane, Hardings Lane, Fair Oak Road

Southern Water will be building a 1km sewer to connect a new housing development, off Winchester Road, just north west of Fair Oak, to its wastewater network.

The sewer will go along Sandy Lane, Hardings Lane and cross Fair Oak Road. Works are expected to be completed by November 2017.

It will start in Sandy Lane, approximately 250m north of the junction with Fair Oak Road and continue in sections working toward Hardings Lane.

Roads will remain open with temporary traffic lights in place, which will be manually-operated during peak times.

This is an essential scheme to ensure a new development can connect to our sewer network. We’re really sorry for any inconvenience and we’ll do all we can to keep impact to a minimum.”

For further information, please visit the website www.southernwater.co.uk/fair-oak